Received $1000 donation toward the construction of walk path.
The engineering and design of the first phase of the walk path project came in at $31,250.00 of which we have received $25,000 from the WYDOT- Teal Grant program and $6,250 will come from the town for match. The engineering and design are complete.
The construction of phase one and the engineering and design of
phase two of the walk path came in at $370,000.
We received $200,000 from the TEAL grant program to proceed with the
construction of Phase I of the walk path. The
town will apply for further funding to help with the $74,000 match.
Began construction August 2009
General contracting (ie. concrete pathway) completed Jan. 2010
Lighting, picnic tables/benches are being ordered to be completed by
May 2010
Second phase design completion date March 2010
1st phase construction completion date June 2010